Out of Hours Working M25 Junction 21a: 6-8 January 2011

Post date: Jan 6, 2011 7:45:49 PM

This is to advise you that we intend to carry out overnight working on the 6, 7 and 8 January 2011. The work being carried out is to install two new gantries either side of junction 21a which will span the slip roads. We do not anticipate this work causing any further disturbance to local residents.

As a guide the following schedule is the expected programme of work however, it is weather dependent and therefore adverse weather conditions may cause the programme to alter.

Thursday 6 January       10pm - 2.30am          Preliminary works preparing for gantry installation 

Friday 7 January         10pm - 2.30am          Preliminary works preparing for gantry installation 

Satursday 8 January      11pm - 6am             Installation of two new gantries       

Regards

Jo Bray 

Community Relations Officer 

M25 Widening Junction 16-23 

Skanska Balfour Beatty Joint Venture 

The M25 junctions 16-23 widening project is being carried out by Skanska Balfour Beatty Joint Venture for Connect Plus working on behalf of the Highways Agency.